The electrical code edition in force in Oregon, with its effective date, the adopting authority and an official link. Factual adoption data only — confirm with your local AHJ.
NEC / NFPA 70 in force in Oregon
2023 Oregon Electrical Specialty Code
2023 Oregon Electrical Specialty Code (OESC), based on the 2023 NEC (NFPA 70)
Adopting authority
Oregon Building Codes Division (BCD) — Electrical and Elevator Board
Authority websiteStatewide code: Oregon adopts the 2023 NEC as the 2023 OESC with state amendments (OAR 918-305, Table 1-E). Administered by the Building Codes Division (Electrical and Elevator Board). The 2026 OESC is in the adoption process with an anticipated effective date of Oct. 1, 2026.
State/province adoption is the baseline. Your local building department may amend it or enforce a different edition — always confirm with the authority having jurisdiction (AHJ) before you design, bid or pull a permit.
Oregon has adopted 2023 Oregon Electrical Specialty Code (OESC), based on the 2023 NEC (NFPA 70) (NEC / NFPA 70) with an effective date of October 1, 2023. The body responsible for adoption and enforcement is Oregon Building Codes Division (BCD) — Electrical and Elevator Board. This is the jurisdiction-wide baseline — your local building department may amend it or enforce a different edition, so confirm with the authority having jurisdiction before you design, bid or pull a permit.
Statewide code: Oregon adopts the 2023 NEC as the 2023 OESC with state amendments (OAR 918-305, Table 1-E). Administered by the Building Codes Division (Electrical and Elevator Board). The 2026 OESC is in the adoption process with an anticipated effective date of Oct. 1, 2026. The official code text is published by the standards body and is free to read online — use the official link above to read it. We link and cite the code; we do not reproduce it.
Oregon has adopted 2023 Oregon Electrical Specialty Code (OESC), based on the 2023 NEC (NFPA 70) (NEC / NFPA 70), effective October 1, 2023. The adopting authority is Oregon Building Codes Division (BCD) — Electrical and Elevator Board. Verified June 28, 2026.
Statewide code: Oregon adopts the 2023 NEC as the 2023 OESC with state amendments (OAR 918-305, Table 1-E). Administered by the Building Codes Division (Electrical and Elevator Board). The 2026 OESC is in the adoption process with an anticipated effective date of Oct. 1, 2026.
It is the specific edition of a model code (for example the 2023 NEC, the 2021 IBC, or CSA C22.1:24) that a state or province has legally adopted and currently enforces. Codes are republished on roughly three-year cycles, and each jurisdiction adopts a new edition on its own schedule — often with amendments — so the edition in force varies by place and by discipline.
Not always. Many jurisdictions set a statewide or provincial baseline edition, but local building departments (the authority having jurisdiction, or AHJ) can amend it or enforce a different edition. Some states leave most adoption to local jurisdictions, and a few large cities such as Chicago and New York City run their own codes. Always confirm with your AHJ.
In the United States: the NEC (NFPA 70) for electrical, the ICC I-Codes (IBC/IRC) for building, the UPC (IAPMO) or IPC (ICC) for plumbing, the IMC/UMC for mechanical, the IFGC/NFPA 54 for fuel gas, and the IFC/NFPA 1 for fire. In Canada: the Canadian Electrical Code (CSA C22.1), the National Building, Plumbing and Fire Codes of Canada and their provincial editions, and CSA B149.1 for gas.
NFPA offers free read-only online access to many of its standards including the NEC, and the ICC publishes its I-Codes through a free online reading room. Canadian codes are typically published by CSA Group or the National Research Council and may require purchase or membership. Each result links to the official source.
Trade codes are copyrighted by their standards bodies (NFPA, ICC, IAPMO, CSA). This directory publishes only factual adoption data — which edition is in force, when it took effect, who the authority is, whether it is amended, and where to read it officially — and links you to the official source for the code text itself.
This record was verified against Oregon Building Codes Division (BCD) — Electrical and Elevator Board and the relevant standards body on June 28, 2026, and is next due for review by December 31, 2026. We publish factual adoption data only — never code text.
Last reviewed June 28, 2026. Estimates are indicative — verify against current product specs and local requirements before ordering.